Wednesday, July 30, 2008

Week 7

This week we are going to be working on getting as much of the sidewalks at the entry to the church done as possible. We will also be finishing up the sidewalk and approach at the north parking lot. That will leave just the entry to complete for the city sidewalks.

We will be cutting and removing concrete in the courtyard to accommodate the new condensers that will be located there. At that same time, we will cut and remove a small portion of the blacktop at the north west approach to the west parking lot so we can have new blacktop installed maybe this week.

On the interior, we are working on drywall and drywall finishing. We are also framing around duct work as it is installed for the roof top units. We may even install the roof top units this week.

It is all starting to come together! Enjoy the most recent pictures.

Nursery:

Children's Area

Primary Room:

Upstairs Conference Room:

Current High School Room:

Tuesday, July 22, 2008

Week 6

This week, sheet rock will start going up! Also, the framing for the entryway on the west side of the building will start. HVAC will be installed by the end of the week, and all of the sidewalks will be completed. You will notice in the pictures that the old tiles on the ceilings have been removed in multiple areas. We are making great progress!

Nursery Area:
Early Childhood Area:

The Primary Room:
Upstairs Conference Room:
Current High School Room:

Tuesday, July 15, 2008

Week 5

This week we are looking to finish up framing, sheet-rock, and pour sidewalks. We are also ordering doors and there is a chance they could push us over our move in time if they are not in stock. Please pray this goes smooth! Same goes for lights. We decided to repaint all foyers and decorate them with art. Our new art pastor Martin French will be in charge of all prints and sculptures.

The Nursery:

Children's Classroom:

The Primary Room:

Upstairs Conference Room (You can see one of our staff, Katie in the back. She is excited!):

Current High School Room being wired:

Wednesday, July 9, 2008

Week 4

Things are moving along very quickly. We have about half of the sidewalks poured and have contractors out for HVAC, mechanical and plumbing. We also will have all of the rough framing done this week.

Children's Classroom:

The Nursery:

The Primary Room:
Upstairs Conference Room:
The current High School Room:
Some of the new sidewalks are poured:


Week 3

This week we got half of the sidewalks torn up and finished up the remaining demolition. Here are some photo updates:

Sidewalks on the East side of the building:


Primary Room on the main floor:


Conference Room:


High School Room looking at the new kitchen:

Monday, June 30, 2008

Plans

Not sure how much of a construction geek you are, but if you are like me, you love this stuff. This is basically all of the activity that will take place in the three main work areas. When it is all said and done, there will be: 
-23 offices and 16 modular workstations. 
-Compliant nursery and early childhood areas will all be remodeled. 
-5 bathrooms will be redone and 3 will be ADA compliant. 
-We will also install A/C in all office areas
-We will install a card key system in the main office entry.
-New sidewalks around perimeter of building
-New flooring
-New paint
-New bathroom fixtures
-New light fixtures
-New office doors with relites
-Wireless network 
-VOIP phone network
-New metal fire escape


North. Main Floor



South. Main Floor


Second Floor

Week 2

Things are going very smooth so far. This week R&H will be removing all of the asbestos tiles from both floors, expanding door openings, electrical , HVAC prep and tear out half of the side walks.


downstairs main floor


Conference room


Nursery


High school room