We will be cutting and removing concrete in the courtyard to accommodate the new condensers that will be located there. At that same time, we will cut and remove a small portion of the blacktop at the north west approach to the west parking lot so we can have new blacktop installed maybe this week.
On the interior, we are working on drywall and drywall finishing. We are also framing around duct work as it is installed for the roof top units. We may even install the roof top units this week.
It is all starting to come together! Enjoy the most recent pictures.