Cabinets are getting put into the Nursery area:
Wednesday, September 3, 2008
Week 12
This week, we are going to finish as much as 95% of the flooring, if not all of it and we'll get our plumbing fixtures set. We are also pouring our exterior stair footings on Thursday and cleaning up around them on Friday. All of the cabinetry will be set by the end of the day Friday along with 75% of all the base. We will be 80% to 85% complete by Friday with the exception of our exterior stair and interior doors! The staff is excited to start moving at the end of next week!
Cabinets are getting put into the Nursery area:
Cabinets are getting put into the Nursery area: