Week 12

This week, we are going to finish as much as 95% of the flooring, if not all of it and we'll get our plumbing fixtures set. We are also pouring our exterior stair footings on Thursday and cleaning up around them on Friday. All of the cabinetry will be set by the end of the day Friday along with 75% of all the base. We will be 80% to 85% complete by Friday with the exception of our exterior stair and interior doors! The staff is excited to start moving at the end of next week!

Cabinets are getting put into the Nursery area:

Work area off the Nursery:

The Primary Room:
One of the cubicles:
The Kitchenette on the 2nd floor:
Shelves & Cabinets in the Copy Room: