Tuesday, July 22, 2008

Week 6

This week, sheet rock will start going up! Also, the framing for the entryway on the west side of the building will start. HVAC will be installed by the end of the week, and all of the sidewalks will be completed. You will notice in the pictures that the old tiles on the ceilings have been removed in multiple areas. We are making great progress!

Nursery Area:
Early Childhood Area:

The Primary Room:
Upstairs Conference Room:
Current High School Room: