Tuesday, September 30, 2008

It's Finished!

It's finally finished! We are in our new space and enjoying it very much. Thanks to Ryan Flood for taking some amazing photos of the remodel.

Holly is enjoying her new space in the front office:

Clockwise from Top Left: Katie, Neisha, Jesse and Callie, working in their new cubicle spaces.

Katie visiting Neisha's new cubicle:

The downstairs kitchenette:

Scott working hard in his new office:

The hallway leading to Rick & Ken's offices:

Wednesday, September 10, 2008

Week 13

It's move-in week! Everything for the build out will be completed on Friday! Pictures of happy staff members in their new spaces will be posted next week. For now, enjoy the last bit of construction pictures!
The Nursery:

The Former Primary Room:
The former conference room:
One of our new bathrooms, with eco-conscious toilets!
The former high school room:
The new main office entry:

Wednesday, September 3, 2008

Week 12

This week, we are going to finish as much as 95% of the flooring, if not all of it and we'll get our plumbing fixtures set. We are also pouring our exterior stair footings on Thursday and cleaning up around them on Friday. All of the cabinetry will be set by the end of the day Friday along with 75% of all the base. We will be 80% to 85% complete by Friday with the exception of our exterior stair and interior doors! The staff is excited to start moving at the end of next week!

Cabinets are getting put into the Nursery area:

Work area off the Nursery:

The Primary Room:
One of the cubicles:
The Kitchenette on the 2nd floor:
Shelves & Cabinets in the Copy Room:

Friday, August 29, 2008

Week 11

This week focused on flooring, landscaping, HVAC, light fixtures, baseboard. It's really starting to fly now. Two weeks left!!!




These are the carpet tiles that are on all of the office floors.




This is old High School room.



New baseboard.



New rear door and sidewalk.


Blurry picture of new bathroom.


New carpet on main floor.



New entry way to office area.



Redone staircase. The old one was actually sinking
and had to be removed.





HVAC for office area and nursery.




New cabinets for copy room.




Bike racks. Pavers will be added next week.



New landscaping around parking area.





Wednesday, August 20, 2008

Week 10

We're getting closer to the finish line! This week at Evangel, the interior painting will be finished, the carpet will start getting laid down, the cabinets will be installed and the door frames will be put in. We apologize for some of the clutter in the pictures, but everything needed to be moved toward the center of the rooms to make way for painting the walls.

Children's Area:

The Nursery Area (this is one of the wall colors!)

Primary Room:

Upstairs Conference Room:

Current High School Room:

Wednesday, August 13, 2008

Week 9

This week during the remodel, you can really start to see things come together. Paint is going on the walls and it looks great! We'll be installing bike racks and a new fire escape. As you can see below, the sidewalks on the front and east side of the buildings are finally complete. We're moving along in the process of remodeling the back entrance as well. Enjoy the pictures!

East Side Sidewalks

Front Entrance Sidewalks

Children's Area

Nursery
Primary Room
New Back Entrance
Upstairs Conference Room

Current High School Room

Tuesday, August 5, 2008

Week 8

This week, the front sidewalks will be finished, the interior drywall will be finished. We've started to re-construct the rear entryway and we'll be starting the prep work for all of the painting. Things are really picking up.

Nursery:

Kids Area:
Primary Room:

Upstairs Conference Room:

Current High School Room: